• July 28, 2014

    Posted by Lynn McIsaac at 8/1/2014
     
    1  
    2  
    3  
    4  
    5  
    6  
    7  
    8  
    Comments (-1)
  • July 18, 2014 Update

    Posted by Lynn McIsaac at 7/23/2014

    School Construction Update

    Submitted by Elizabeth Lewis, School Building Committee

     1

    It has been a very busy and exciting month for the teachers and administrators at the middle and high schools.  On June 9th, Dimeo Construction Company received the Certificate of Occupancy and turned the new middle and high school building over to Duxbury Public Schools.  As the school year wound down, the teachers sorted and packed thousands of boxes of books and equipment to be moved into the building.  Within days of the end of the school year, surplus items were sold at the schools’ yard sale raising $4,500 for the Town and movers had completed the move.  Throughout the month of June, deliveries of new furniture and equipment arrived daily. 

    2  

    The vacated middle school has been fenced and abatement and hazardous material removal has begun; demolition is scheduled to begin in September and continue for approximately one month.  The same work will occur at the high school, with a schedule that lags behind approximately two weeks. 

    3  

    The building continues to be a very active site as construction workers finish punch list items, vendors install technology equipment, and furniture and equipment is delivered and assembled.   To that end, we remind residents that the building is not open to the public for visits or tours at this time unless required for school related business.  All visitors must sign in at the middle school office and will be escorted to their destination.

    4

    We look forward to putting the finishing touches on the building to be ready for the ribbon cutting ceremony on August 28th at 2:00 p.m.  Following the ceremony, the public is welcome to tour our beautiful new middle and high school.   Duxbury Public Schools will provide updates on changes to traffic patterns and parking later in the summer.  Please note that the Superintendent’s office and School Business office have been relocated to the Canty Wing of Chandler Elementary School.

    5  
    6  
    7  
    Comments (-1)
  • June 20, 2014 Update

    Posted by Lynn McIsaac at 6/24/2014
    pic 1  
    pic 2  
    pic 3  
    pic 4  
    pic5  
     
    Comments (-1)
  • May 31, 2014 Update

    Posted by Lynn McIsaac at 6/3/2014

    School Building Project Update Week Ending May 31, 2014

    1  

    2  
    3  

    On site work accomplished this past week included:

    4                                    

    ·         Mechanical, plumbing and electrical working on testing and close out activities throughout the building.

    ·         Painting continues throughout the building.

    ·         Site work included installing paving and sidewalks.

    ·         Parking/drive light poles installed

    ·         Landscaping work including planting and mulching at building perimeter.

    ·         Punch list process underway.  Trades are taking care of their punch list issues.

    ·         Work crews ranged from 75 to 95 workers per day.

    5  

    6  

    Work planned for the week of June 2 includes:

     

    ·                     Mechanical, plumbing and electrical trades continuing working on testing.

    ·                     Site work continues. 

    ·                     Landscaping continues.

    ·                     Clean up continues.

    ·                     Testing and startup operations underway.

    7  
    Comments (-1)
  • May 24, 2014 Update

    Posted by Lynn McIsaac at 6/2/2014

    School Building Project Update Week Ending May 24, 2014

     

    On site work accomplished this past week included:

    1            
    2  
     
    3  

    ·         Mechanical, plumbing and electrical working on testing and close out activities throughout the building. 

    ·         Plumbing, electrical and elevator inspections took place this week.

    ·         Painting continues throughout the building.

    ·         Site work included installing curbs and work on sidewalks.

    ·         Landscaping work including planting and mulching at building perimeter.

    ·         Punch list process underway.  Trades are completing items from their punch list issues.

    ·         Work crews ranged from 98 to 114 workers per day.

    4

    5  
    6  

    Work planned for the week of May 26 includes:

     

    ·                     Mechanical, plumbing and electrical trades continuing working on testing.

    ·                     Interior finishes underway at Area “D”.

    ·                     Site work continues. 

    ·                     Landscaping continues.

    ·                     Next sidewalk pour scheduled for Tuesday.

    ·                     Testing and startup operations underway.

    Comments (-1)
  • May 17, 2014 Update

    Posted by Lynn McIsaac at 5/30/2014

    School Building Project Update Week Ending May 17, 2014

     1

    2  

    On site work accomplished this past week included:

    3       
    4  

    ·         Mechanical, plumbing and electrical working on finishes and close out activities throughout the building.

    ·         Painting continues throughout the building.

    ·         Site work included installing curbs and work on sidewalks.

    ·         Landscaping work including planting and mulching at building perimeter.

    ·         Punch list process underway.  Punch list at Area D performed this week.

    ·         Work crews ranged from 119 to 128 workers per day.

     5

    Work planned for the week of May 19 includes:

    6  

    ·                     Mechanical, plumbing and electrical trades continuing working on testing and training.

    ·                     Interior finishes underway at Area “D”.

    ·                     Site work continues. 

    ·                     Landscaping continues.

    ·                     Testing and startup operations underway.

    Comments (-1)
  • May 10, 2014 Update

    Posted by Lynn McIsaac at 5/13/2014

    School Building Project Update Week Ending May 10, 2014

     1

    2  

    On site work accomplished this past week included:

    3   
    4                                  

    ·         Mechanical, plumbing and electrical working on finishes and close out activities throughout the building.

    ·         Painting continues throughout the building.

    ·         Wall and floor tile continues throughout the building.

    ·         Site work included installing curbs and work on retaining wall and sidewalks.

    ·         Landscaping work including planting and mulching in courtyards.

    ·         Punch list process underway.  Punch list at Area D performed this week.

    ·         Work crews ranged from 139 to 147 workers per day.

    5  

    Work planned for the week of May 12 includes:

     

    ·                     Mechanical, plumbing and electrical trades continuing working on finishes.

    ·                     Kitchen equipment startup.

    ·                     Interior finishes underway at Area “C” and main concourse.

    ·                     Site work continues. 

    ·                     Landscaping continues.

    ·                     Testing and startup operations underway.

    6  
    7  
    Comments (-1)
  • May 3,2014 Update

    Posted by Lynn McIsaac at 5/12/2014

    School Building Project Update Week Ending May 3, 2014

    1

    On site work accomplished this past week included:

    2                                    

    ·         Mechanical, plumbing and electrical working on finishes and close out activities throughout the building.

    ·         Painting underway throughout the building.

    ·         Gym bleachers installed.

    ·         Wall and floor tile continues throughout the building.

    ·         Site work included installing curbs and work on retaining wall and sidewalks.

    ·         Landscaping work including planting and mulching in courtyards.

    ·         Punch list process underway.

    ·         Work crews ranged from 148 to 164 workers per day.

    3  

    4  

    Work planned for the week of May 5 includes:

     

    ·                     Mechanical, plumbing and electrical trades continuing working on finishes.

    ·                     Interior finishes underway at Area “C” and main concourse.

    ·                     Site work continues. 

    ·                     Landscaping continues.

    Comments (-1)
  • April 26,2014 Update

    Posted by Lynn McIsaac at 4/29/2014 3:25:00 PM

    School Building Project Update Week Ending April 26, 2014

    1  
    2  

    On site work accomplished this past week included:

    3  
    4                                  

    ·         Mechanical, plumbing and electrical working on finishes throughout the building.

    ·         Painting underway throughout the building.

    ·         Wall and floor tile continues throughout the building.

    ·         Terrazzo floor nearing completion.

    ·         Site work included sidewalks and prep of courtyards.

    ·         Landscaping started this week.

    ·         Punch list process underway.

    ·         Work crews ranged from 154 to 170 workers per day.

    5  

    Work planned for the week of April 28 includes:

    6  

    ·                     Mechanical, plumbing and electrical trades continuing working on finishes.  Also involved with testing, startup and training.

    ·                     Interior finishes underway at Area “C” and Area “D”.

    ·                     Terrazzo floor continues, 98% + complete.

    ·                     Site work and landscaping continues. 

    7  
    Comments (-1)
  • April 18, 2014

    Posted by Lynn McIsaac at 4/29/2014

    School Building Project Update Week Ending April 18, 2014

     1

     2  

    On site work accomplished this past week included:

    3                                   

    ·         Mechanical, plumbing and electrical working on finishes throughout the building.

    ·         Painting underway throughout the building.

    ·         Wall and floor tile continues throughout the building.

    ·         Terrazzo floor nearing completion.

    ·         Site work included sidewalks and prep of courtyards.

    ·         Punch list process underway.

    ·         Work crews ranged from 148 to 157 workers per day.

    4  

    Work planned for the week of April 21 includes:

    5  

    ·                     Mechanical, plumbing and electrical trades continuing rough in work at Area “C” and Area “D”; also working on finishes.

    ·                     Interior finishes underway at Area “C” and Area “D”.

    ·                     Terrazzo floor continues, 95% + complete.

    ·                     Site work continues.  

    Comments (-1)