Project Timeline

Spring 2012 - Pre-construction work, final design, bidding

Summer - Site preparation behind DMS: fencing, access, utilities

September – Foundation work for academic building begins

November – Construction of field house begins

December – Structural steel work begins for academic building

Summer 2013 – Field house completed

June 2014 – Academic building completed, abatement and demolition of DMS/DHS begins

August - Students occupy new academic building

January 2015 – Abatement and demolition of DMS and DHS completed

Summer – Site work and improvements for both sites completed